Main Street Reconstruction Update - August 10, 2018

Main Street Reconstruction Update - August 10, 2018

There has been excellent construction progress to date and with our Contractor proceeding south of the Poyntz Street intersection in the coming weeks the end is in sight. 

JB Enterprises Ltd. has completed the following work for the week ending August 10th, 2018:

  • The Sanitary Bypass has been moved south from Poyntz Street to Jeffrey Street;
  • Traffic Controls have been moved to close access to Poyntz Street, Jeffrey Street, and Main Street to Edward Street;
  • Pulverized Asphalt from Poyntz Street to 100 m North of Edward Street;
  • Continue Water Main and services heading south towards Poyntz Street
  • Robert Street and Main Street Intersection Open to East/West Traffic on August 3rd;
  • Sanitary sewer and Storm sewer including services complete from Robert Street to Poyntz Street;
  • Traffic Lights Removed in the Poyntz Street and Main Street Intersection;
  • Placement of Road Base Granulars has started on Main Street Heading south from Robert Street;
  • Temporary Water Main set up from Edward Street to Thompsons Road;
  • Sanitary and Storm Main line completed through the Poyntz Street Intersection.

The following items are scheduled to be completed for the week of August 13th, 2018 to August 17th, 2018:

  • The Sanitary Bypass will be relocated to the south from Jeffrey Street to Edward Street;
  • Continuation of the Sanitary and Storm servicing heading south from Poyntz Street;
  • Continuation of the Water Main installation heading south towards Poyntz Street and begin Flushing and Testing;
  • Continue Street Light Relocations from Simcoe Street to Robert Street;
  • Sidewalk Installation from Simcoe Street to Robert Street (East Side);
  • Traffic Signalization work continues in the Robert Street and Main Intersection;
  • Boulevard Paving Stones installation from Wolfe Street heading South;
  • Placement of Road Base Granulars on Main Street from Robert Street continuing south.

With the reopening of the Robert Street intersection in the eastbound and westbound direction only, stop signs have been placed in the appropriate locations.  Please obey the stop signs as they will allow pedestrian traffic to safely cross the intersection until such time as the traffic signalization is in place. 

The intersection at Poyntz Street and Jeffery Street will be closed as the work between the intersections will continue.  The detour has been set up at Edward Street to send all traffic east and west bound around to Robert Street East.  A map has been attached to identify the route to be taken if you are looking to get to the west or east end of town.  JB Enterprises has assured both the Town and the Village Square Mall merchants that access will be provided at all times to the property off Main Street.  This will require the installation of a temporary access so please watch for the Mall access locations as they may change over the course of the next 2-3 weeks.   

Thank you to everyone for your continued patience and understanding.  Should you have any questions or concerns please contact the Public Works Department at 549-7992 or visit the Town of Penetanguishene website at www.penetanguishene.ca.


Bryan Murray, P. Eng.
Director of Public Works
Town of Penetanguishene

 