NOTICE OF ROAD RESURFACING NETTLETON DRIVE, SHANAHAN LANE LEVI SIMON TRAIL & FORESTDALE DRIVE

Posted on Thursday July 13, 2017

THE TOWN OF PENETANGUISHENE

PUBLIC WORKS DEPARTMENT

 

NOTICE OF ROAD RESURFACING

 

NETTLETON DRIVE, SHANAHAN LANE

LEVI SIMON TRAIL & FORESTDALE DRIVE

 

 

Please be advised that Georgian Paving and Construction, in conjunction with Roto Mill, will begin the resurfacing the roads listed below, starting the week of Monday July 17th, 2017.

 

  • Nettleton Lane  – Main Street to dead end – 720 m
  • Shanahan Lane  – Main Street to John Street – 720 m
  • Levi Simon Trail – Brock Street to Burke Street – 400 m
  • Forestdale Drive - Oakdale Drive to Sandy Bay Road - 330 m

 

This project is scheduled to be completed in approximately 2 to 3  days and will include the pulverization of the existing road surface, grading of the granular road base and the full depth restoration of the asphalt surface.  The road during this period will be open to local traffic only and will include lane reductions as part of the overall traffic control plan.

 

We apologize for any inconvenience that this may cause. If you have any questions or concerns regarding the above please contact the undersigned at 705-549-7992

 

 

 

Bryan Murray, P.Eng.                                          Keith Kelly

Director of Public Works                                    Road Supervisor